Over the years, WATCOM has undertaken projects within and outside the county. The following are some the accomplished projects since 2013


Rehabilitation of Omoyo Gravity Flow Scheme (GFS) in Zombo District Completed 02/09/2017

AECOM Provision of pumping and water sampling on three boreholes in Murchison Falls National Park Completed 11/10/2016
Hydro geological survey for 25 Boreholes in Pader District Completed 30/9/2016
Design and installation of a pilot drip irrigation system for one acre in Nakivale Refugee Settlement Isingiro District Completed 31/08/2016
Construction of two 50m3 underground tanks installed with Rope Pumps at Olekai Primary School in Asamuk ADP and Gweri Primary school in Gweri ADP Under Soroti Cluster Completed 20 /07/2016
Construction of one 50m3 underground tank fitted with Rope Pump at Kituntu Primary school in Buikwe DistrictCompleted 21/6/2016
Design, construction supply and installation of a solar powered mini-water supply system at Kirinda village Kasege Parish, Kapeke Subcounty in Kiboga District Completed 16/6/2016
Feasibility and detailed design of Nabiganda Parish Water Supply System in Kachonga ADP Butaleja DistrictCompleted 31/7/2016
Testpumping of one borehole at St Peter’s Primary School and Topographic Survey for a water supply system in Matale RGC in Buikwe District Completed 18/3/2016
Construction of four 50m3 underground tanks fitted with Rope Pumps at Nsono, Kasingweire Itakaibulo and Nawambwa primary schoolsin Nankoma ADP in Bugiri DistrictCompleted 21/4/2016
Construction of one Ordinary spring and one Box spring in Ngogwe Subcounty Buikwe DistrictCompleted 30/03/2016
Test pumping of one borehole at Lubiriha Cholera Treatment in Kasindi DRCCompleted 03/12/2015
Hydrogeological Survey in Mikomago Parish Masaka DistrictCompleted 12/12/2015
Rehabilitation of 4 boreholes in Adropi, Ofua and Pachara Subcounty in Adjumani DistrictCompleted 25/02/2016


Drilling of one borehole in Najjera, Wakiso District
Construction of two 50m3 underground tanks fitted with Rope Pumps in Namanyonyi ADP Mbale District 28/10/2015
Drilling of one Shallow well in Naluvule village Nansana Town Council Wakiso District
Construction of one 20m3 Ferro cement tank in Bugiri District 15/10/2015
Construction of 12 shallow wells in Busabi,Paya and Sop Sop Subcounty in Tororo and Butaleja District under Paya cluster 28/01/2016
Siting 1 production bh in Muni Technical Institute in Arua District 03/04/2015
Assessment of 1 borehole at Bwendero farm, Hoima District
Construction of 1 ferrocement tank in Lunyo ADP, Busia Cluster & 1 SW in Gulu Cluster
Rehabilitation of 6 boreholes in Nakasongola District 13/05/2015 12/07/2015
Drilling one borehole in Nabiyagi Mukono District 28/03/2015 27/04/2015
Construction of five 20m3 ferro cement tanks in Mpigi Cluster 30/03/2015 28/06/2015
Construction of contractor's office block in Kayunga District 28/02/2015 05/07/2015
Construction of 1 SW in Nansana Wakiso District 25/03/2015 04/04/2015
Construction of 1 SW in Lweza Wakiso District 18/03/2015 05/04/2015
Feasibility Study, protection, construction of 7 springs in Ngogwe ADP,Ngogwe Sub-County Buikwe District 23/01/2015 23/04/2015

Siting & drilling supervision of 14 boreholes in Zombo District 01/05/2014 01/05/2015
Drilling of 2 boreholes in Amuria District 10/08/2014
Drilling of one borehole in Nakisunga Mukono District 10/02/2014
Stone Pitching and Drainage Construction along Mbarara - Ntungamo Sections 28/08/2014 01/01/2015
Design of Livestock Research Centre 20/09/2014
Pumping and Sampling of one borehole in Bugungu and Tangi camp 28/09/2014
Construction of 3 ferro cement tanks in Nakasongora District 19/07/2014 26/08/2014
Pumping and Sampling of one borehole in Bugungu and Tangi camp 01/07/2014 01/07/2014
Siting 1 production well in Lyantonde District 01/07/2014 01/07/2014
Rehabilitation of 23 boreholes in Northern Uganda, 5 boreholes in Paicho Bungatira ADP,10 boreholes Aber and Minakulu ADP and 8 boreholes in Koro Bobi ADP 01/06/2014 17/09/2014
Siting, drilling, test pumping and hand pump installation of 3 boreholes in Rhino Camp in Arua district 01/06/2014 14/07/2014
Test pumping/Sampling of four boreholes for Total E&P in MFNP 01/06/2014 01/06/2014
Drilling of 1 borehole in Nawanyango S/C, Kamuli District 01/05/2014 01/06/2014
Test pumping/Sampling of four boreholes for Total E&P in MFNP 01/04/2014 01/05/2014
Hydrogeological survey for production wells in Nakaseke District 01/03/2014 March
Hydrogeological survey for 2 production wells in Eastern Uganda 01/03/2014
Construction of 2 springs and 7 manual drilled wells in Kizaranfumbi, Hoima district 01/03/2014 23/06/2014
Survey and drilling of one production borehole in Mubende District 01/03/2014
Geophysical survey for 1 borehole in Kiterede, Kyotera in Rakai District 01/03/2014
Geophysical survey of 4 production wells in Wobulenzi & Luweero 01/03/2014
Survey and drilling of one production borehole in Bukerere Kayunga District 01/03/2014
Test pumping of one borehole for a factory in Bugolobi 01/03/2014 01/03/2014
Design of Adida and Fada bridges in Zombo District 01/02/2014
Siting, drilling test pumping and hand pump installation of one borehole in Semuto, Nakaseke District 01/01/2014 01/01/2014


Topographic survey of 209km for water supply phase 3 of Rwanda water supply/ Japan Techno Japan Techno/ Foracky AFRICA RWANDA Kayonza, Gasibo, Nyagatare, Kirehe Rwanda
Hydrological survey (flow measurements and water quality analysis) of 6 water sources in Ngoma, Kayonza, Gatsibo and Kirehe Districts in Rwanda Japan Techno/ Foracky AFRICA RWANDA Kayonza, Gasibo, Nyagatare, Kirehe Rwanda
Borehole Siting, drilling supervision and contract Management for 25 boreholes in South Sudan ZOA Refugee Care Sudan Yei South Sudan